Tuesday
Dec142010
Aircraft Hangars, West Apron Naval Air Facility - El Centro, CA
![]() |
|
This design-build project involves the construction of two new 32,000 square foot hangers. Specific items of work are demolition, grading, drainage, underground utilities, cast-in-place concrete, pre-engineered building structure, installation of specialized fire fighting equipment, apron paving and erosion control. T.B. Penick’s expertise with structural concrete was a critical and cost saving benefit to the design of the structures. During the design stage, Penick-Triton led a value-engineering effort to save hundreds of thousands dollars in materials usage on the project, and was able to deliver the successful completion of the project eight months ahead of schedule.